Local utility funds 25.4% of Odessa School District
program cost through energy incentives.

The Client: Odessa School District, Odessa Washington
Buildings: High School, Elementary, 2 Gymnasiums, Central Plant, Shop, Bus Garage
Scope of Work: Networked building automation, lighting retrofit (1880 Lamps) and replacement (706 Fixtures), lighting occupancy control, boiler restoration, ventilation improvements, boiler isolation, on-demand domestic hot water, door replacement and window coverings, mechanical system re-commissioning, safety improvements.


Financial
ANNUAL GUARANTEE GUARANTEE FIRST SIX MONTHS ACTUAL FIRST SIX MONTHS PERCENT OF GUARANTEE
$13,543.00 $6,771.00 $12,317.00 181.9%

Comments From The District

From the Superintendent - "We thank you and your staff for the difference you have made. Your team brought a level of expertise and professionalism to the table that is unprecedented in my many years of experience as a superintendent."
"We have had the best start in terms of staff and student comfort than ever before. You have been able to accomplish this for us, and at the same time are saving us thousands of dollars. The project costs were consistent with the contract price. This is most unusual as projects typically cost more than the bid."
"The scope and sequence from analysis to project completion took 12 months. During that time period your firm met every timeline and verbal commitment. We thank you and your staff for the difference you have made."




Cafeteria Lighting Replacement

Before

After



District Benefits
  • Energy reduction KW= 39%, KWH/ YR= 13,367
  • Improved light levels and color rendering
  • Reduced heat output, reduced repair and lamp replacement costs, reduced energy